ALL car parks are very busy this Labour Day long weekend, with limited drive-up spots available. Please consider alternative transport options.  If you do have a car park booking, please have your QR code ready for a smooth entry and exit and allow extra time to find a spot. Our roads and car parks may have changed since your last visit. Due to ongoing construction in the T123 car park Pick up and Drop off areas, passengers should plan for potential delays of up to an hour during peak times. Learn more about the Naarm Way Stage 2 project: https://www.melbourneairport.com.au/plan-ahead To avoid congestion, we recommend using the equivalent pick-up and drop-off facilities at nearby Terminal 4 car park, just a short 10-minute walk from Terminals 1, 2, and 3. Simply drive to the Terminal 4 Car Park and proceed to Level 2 for Drop off or Level 1 for Pick up. Thank you for your patience while we are building your airport.

墨尔本机场开始对东西向跑道进行必要的安全工程。

2026年1月22日

墨尔本机场将开始每十年一次的东西向跑道维护,最多需七个月的夜间关闭,以确保跑道未来安全运行。

该项目包括沥青重铺、线路标记、开槽以及对09/27跑道东段的航空地面照明系统升级,该跑道长2286米,是墨尔本机场两条跑道中较短的一条。

施工将于1月21日至8月期间,周一至周五晚上10点至早上6点进行,具体时间视天气情况而定。

在这些时间段,所有抵达和起降墨尔本机场的飞机都将使用南北向跑道,这可能会让航线下方的乘客产生更多噪音。

该项目需要在跑道中间宽27米的一段路段铺设1万吨新沥青。

墨尔本机场航空主管吉姆·帕拉肖斯表示,澳大利亚最大24小时机场的运营需求,已经过了细致的规划,以平衡安全、社区影响和运营需求。

他说:“这些关键的维护工作旨在确保东西向跑道保持良好状态,支持未来10至12年的飞机起降。”

“在全天候无宵禁机场继续运营的同时关闭我们的两条跑道之一具有挑战性,但夜间关闭确保我们在一天中最繁忙的时段保持最大运营灵活性。

“关闭意味着在夜间维护期间起降的飞机将使用现有的南北向跑道,因此机场北部和南部的社区可能会在此期间经历额外的飞越。

“我们认识到这可能会带来干扰,衷心感谢当地社区在这项重要工作完成期间的耐心等待。

“在这些工程进行的同时,我们还在规划并进行第三条跑道的早期施工,该跑道计划于2031年开放,将支持墨尔本未来的发展。”

任何对跑道覆盖工程有疑问的人都可以联系 community@melair.com.au 噪音投诉则可拨打航空服务的噪音投诉与信息服务(NCIS)电话1800 802 584,或在线联系 https://www.airservicesaustralia.com/community/environment/aircraft-noise/about-making-a-complaint。